How JustAnswer Works:
  • Ask an Expert
    Experts are full of valuable knowledge and are ready to help with any question. Credentials confirmed by a Fortune 500 verification firm.
  • Get a Professional Answer
    Via email, text message, or notification as you wait on our site.
    Ask follow up questions if you need to.
  • 100% Satisfaction Guarantee
    Rate the answer you receive.
Ask Alice H Your Own Question
Alice H
Alice H, Solicitor/Partner
Category: Law
Satisfied Customers: 2850
Experience:  Partner in national law firm
30932268
Type Your Law Question Here...
Alice H is online now

iv got a client iv been doing a refurbish for, patio / kitchen

Resolved Question:

iv got a client iv been doing a refurbish for, patio / kitchen / shower room / knock though
we been working on egg shells good days bad days, she ask me & my team not to do any more work at her home after 6 weeks working, as she is not happy with the work, she will not let me finish first ?
Submitted: 3 years ago.
Category: Law
Expert:  Alice H replied 3 years ago.
My name isXXXXX and I'm happy to help with your question today.

What exactly would you like to know about this?
Customer: replied 3 years ago.

I need to know what to do next ?

Expert:  Alice H replied 3 years ago.
If the customer does not want you to complete the job, then that is her choice: you can offer to complete the job but she doesn't have to accept. As I say its her choice. But stopping you from doing the job means that she is pulling out of your agreement. She is basically in breach of contract and you are entitled to be paid for the job you've done.